0207 993 6222

info@tandtgroup.co.uk

Case Studies

Case Studies

Tariro House 40 – 41 Newington Green N16

Tariro House Demolition Strip Out by TandT Group - case studies
Tariro House Strip Out Demolition by TandT Group

Our case studies include this three storey commercial space totaling 8200 SqFt which was completed in June 2016. The works consisted of the following:

  • Strip Out of all ceilings, partition walls, kitchens, bathrooms and M+E Services;
  • Demolition of lift shaft;
  • Structural walls propping and demolition;
  • Increasing structural openings;
  • Infill openings.

BBC Retail Unit

BBC Retail Unit Isolation and Strip Out by TandT Group - case studies
BBC Retail Unit Strip Out and Isolation by TandT Group

Completed in July 2016. This retail unit required stripping back to shell.
The works were carried out over a one week period and consisted of:

  • Isolation and strip out of certain aspects of mechanical and electrical installations.

Removal of

  • Marble and stainless steel counters;
  • Industrial oven;
  • Floor coverings;
  • Commercial walk in fridge;
  • FF&E.

Norfolk House 31 St James Sq SW1

Norfolk House Strip Out and Dilapidations by TandT Group - case studies

T&T Group completed a strip-out and dilapidations for our client Stanhope Plc. The works comprised of the following:

  • Removal of office furniture and store rooms;
  • Removal of carpet tiles.

Gordon House Greencoat Place SW1

Gordon House Lead Paint Removal by TandT Group - case studies

T&T Group have recently completed Lead Paint Removal for our client, Contrakt Ltd. The works comprised of the following:

  • Closed circuit Blasting to all steel beams and columns to remove all lead contaminated paint;
  • Wet blasting steels once cleaned to achieve desired profile for Intumiscent primer application;
  • Dryblasting any flash rusting;
  • Apply Sherwin Williams specialist coating primer within controlled environmental conditions.

Imperial Works Kentish Town NW5

Imperial Works Strip Out and Lead Paint Removal by TandT Group - case studies

T&T Group completed a stripout of this five floor office for our client, The Thornton Partnership. The works comprised of the following:

  • Removal of all partition and block walls;
  • Removal of plasterboard ceilings;
  • Removal of wood flooring, stone floor tiles and floor screeds;
  • Lead Paint Removal;
  • M&E Services inc all sub mains;
  • Core Staircase to all floors;
  • Demolition of all lift shafts;
  • Removal of render to expose brickwork.

35 George Street W1

35 George Street Strip Out by TandT Group - case studies

T&T Group completed a stripout of this basement area mock up display.
The works comprised of the following:

  • Full toilet block and office space mock ups – Partition walls, M&E services, reinforced concrete slabs, MF ceilings and all other fixtures and fittings.

38 Rosebury Avenue EC1R

38 Rosebury Avenue Strip Out by TandT Group - case studies

T&T Group completed a stripout of this four floor office. The works comprised of the following:

  • Removal of Partition walls, ceilings and flooring;
  • Removal of all office furniture and fixtures and fittings.

56 Muswell Hill N10

56 Muswell Hill Strip Out by TandT Group - case studies

T&T Group completed a stripout of this bar/nightclub/and nursery school. The works comprised of the following:

  • Removal of fixtures and fittings,white goods etc throughout;
  • Exploratory works – exposure of structure build up.